January 6, 2023
Roof Decking and Interior Framing










January 13, 2023
Roof Decking and Interior Framing






January 20, 2023
Retaining Wall Footings, Roof Decking, Porch and Fireplace Slabs







January 27, 2023
January Update from our Project Manager Craig Gustafson
- Framing construction approximately 80% complete
- Trusses were installed in December
- Tongue and Groove (T&G) roof decking 95% complete
- When roof decking is complete Dorman will begin building dry-out
- Retaining Wall footing excavation is complete
- New underground electrical will be 100% underground
- EWEB awarded a $10,000 grant to apply to service entrance facilities
- A 1,000-gallon propane tank will be installed by R&D Propane
- Curtis Equipment has revised kitchen appliance design based on budget
- Billy Pruitt is now providing nighttime security living on-site
- Purchase of remaining construction components continues





February 3, 2023
Entrance Work, Electrical Ducting, Excavations and a Fly-By!





February 10, 2023
Work Continues on Retaining Wall and Roof





February 17, 2023
Retaining Wall Construction, Chimney Started, Carpentry Continues









February 24, 2023
More Retaining Wall Construction, Chimney , Roof Vapor Barrier









March 4, 2023
Exciting Progress Continues Outside!










March 11, 2023
Retaining Wall, Windows, & Patios







March 17, 2023
Mantel, Patio, Siding, & Retaining Walls









March 24, 2023
Siding and Siding Trim
Notes from Project Manager Craig Gustfson March 20:
All of the windows are installed.
The retaining wall is completed.
The exterior siding is nearing completion.




March 31, 2023
A Slow Week
Driveway Staked, Siding Caulked, Custom Doors Being Built