2023 CONSTRUCTION CONTINUES October – November

October 6, 2023
Kitchen Floor Surfacing Completed
Getting Ready to Install Doors
Preparation for Buried Propane Tank Underway

October 13, 2023
Project Manager Reports Upcoming Tasks
Doors and Trim Material On-Site
Electricians Installing Lighting

October 20, 2023
Lighting Fixtures Being Installed
More Doors Ready for Installation
Awaiting Bathroom & Hallway Tiling

October 27, 2023
Things are Happening!
Gas Fireplace and Flue Installed
Window Trim Complete
Door Installation Underway
Patio Railing Installation Work
Hardwood Flooring Delivered
Tile To Be Installed after Door Jams are in Place
Exterior Painting Underway

November 3, 2023
Lots of Activity
Gutters Being Installed
Door Installation Underway
We’re Gonna Have a Kitchen!

November 10, 2023
A Busy Week at the VMCC
Exterior Painting Continues
More Door Installations
Kitchen Work Underway
Rumor Has It: Flooring Next Week

November 17, 2023
Take a Look at Where We Are!!
Hardwood Floor
Service Area Tiles
HVAC on Site
Kitchen Venting being Installed

November 22, 2023
Thanksgiving – A Short Work Week
Community Room Hardwood Floor Finished
Tiling in Restrooms and Service Entrance Finished
Working on Fireplace Hearth

search previous next tag category expand menu location phone mail time cart zoom edit close