April 8, 2023
No Construction Activity — Too Wet for Roofing and Interior Work
On Hold for Dry Weather







April 15, 2023
The VMCC Board Tours the Site. Looking Good!
Still Too Wet! On a Weather Hold. Need 2 Weeks of Dry Weather for Roofing









April 22, 2023
Still Too Wet! On a Weather Hold. Need 2 Weeks of Dry Weather for Roofing
But — Maybe Spring is Finally Here. Good Weather Ahead
Electrical Meter Base & Generator Switch Construction is Started
VMCC Info Booth at the Wooden Boat Festival



April 28, 2023
Jesse Elliott Did A Drone Flyover & Inside Tour (Link)
Electrical Transformer Vault and Conduit to Meter Base Complete
Rough-In Plumbing Is Underway
Roofing Insulation is Staged Inside










May 6, 2023
Still Waiting for Roof Dry-Out; Good Weather Ahead
Plumbing Rough-In Continues
Ready for Driveway Work






May 12, 2023
Still Waiting for Roof Dry-Out; Has Started
Plumbing Rough-In Complete
Electricity to Meter Base; Pre-Wiring Underway
Grading and Compaction on Patio and Around The Structure








May 19, 2023
Got Weather! Gettin’ Roof
Progress on HVAC
Plumbing Drain Work Begins






May 26, 2023
Got Weather! Roof Got Metal!
Exposed Beams Sanded and Ready for Finish
Plumbing and Electrical in Progress
More Grading and Compacting Work Done
Forms for Concrete Apron Around Building